Major Project: Randall Reservoir/Water Tank
Project Type:
Water
Project Status:
Approved and Under Construction
Location:
Reservoir
1300 East 2100 North
North Ogden ,
UT
84414
See map: Google Maps
The Randall Reservoir project scope is to demolish the existing 500,000-gallon water storage reservoir tank and replace it with a 2,000,000-gallon water storage reservoir tank. The reservoir will be fully enclosed concrete and conventional rebar reinforced concrete cylinder, with a 24-foot tall wall, from top to bottom.
The schedule (weather permitting) is as follows:
RANDALL TANK SCHEDULE
- FORM BASE OF TANK 9/5/2023
- TIE REBAR BASE 9/5/2023 -9/18/2023
- SEET WATERSTOP, SCREEDS 9/19/2023
- POUR BASE 9/20/2023
- SET INSIDE FORMS WALLS 9/21/2023 – 9/25/2023
- TIE WALL REBAR 9/25/2023 – 10/2/2023
- FORM OUTSIDE WALL 10/3/2023 -10/5/2023
- POUR WALLS 10/6/2023
- STRIP INSIDE WALL FORMS 10/9/2023 – 10/11/2023
- STRIP OUTSIDE WALL FORMS 10/12/2023 – 10/13/2023
- POUR COLUMNS 10/6/2023 – 10/11/2023
- SHORING 10/11/2023 – 10/25/2023
- TIE REBAR ROOF 10/25/2023 – 11/9/2023
- POUR LID 11/13/2023
- TEAR OUT SHORING 11/20/2023 – 11/27/2023
- CLEAN TANK 11/27/2023 – 12/1/2023
- FILL TANK 12/1/2023 – 12/8/2023
- BACKFILL WEATHER PERMITTING 12/12/2023
Projected project cost estimate: $2,200,000